Rectification · Cost and scope
What does it cost to bring passive fire up to scratch?
There is no honest per-building price for passive fire rectification, because the cost depends almost entirely on what is wrong, how much of it there is, and how hard it is to reach. The biggest single factor is usually access, not materials. The way to get a reliable number is to survey first, group the defects into repeatable repairs, and price those groups. A quote given without a survey is either padded to cover the unknowns or will come back with variations.
What drives the cost
- How many defects, and how alike they are. Fifty identical penetrations in one riser cost far less per item than fifty different problems across ten floors.
- Access. Ceiling heights, occupied areas, after-hours work, scaffolds and lifts, permits and escorts.
- What has to be opened up. Ceilings and linings removed and reinstated by other trades often cost more than the fire work itself.
- The building's age. Asbestos checks and controls in older buildings add time and cost.
- Evidence. Unidentified systems may need investigation before a repair can be chosen.
- Fire doors. Repair, rehang or full doorset replacement are very different prices. Asbestos-core doors add to all of them.
- Steel protection. Patch repairs are cheap. Re-protecting whole members is not.
- Records. A register, photographs and certification are part of the job, not an extra.
How to get a price you can rely on
- Start with what you have. Any previous inspection report, defect register or photographs.
- Get a survey if the records are thin. It turns guesses into a list of items. See What is a compartmentation survey?
- Group the defects. Repeatable repairs get a rate. Exceptions get looked at one by one. See How do you turn a defect register into a rectification scope?
- Agree access and working hours up front. These change the price more than anything else.
- Compare quotes on the same scope. Same items, same records, same certification.
Why the cheapest quote can cost more
- It may not include opening up and making good.
- It may not include photographs, a register or certification, which the owner then cannot use as evidence.
- It may use products that do not match a tested system for the actual condition.
- It may exclude asbestos controls that are then added as a variation.
Spreading the cost
Not everything has to be fixed at once. A sensible programme fixes the highest-risk items first — escape routes, fire doors, open penetrations in key walls — and stages the rest. Under Regulation 48A of the Building Regulations 2012, the owner of a Class 2 to 9 building in Western Australia must keep building fire integrity performing, so a staged plan should still have an end date. More in What does a WA building owner have to do about passive fire?
What to do next
Send the building address and age, any inspection reports or defect registers, photographs, drawings if you have them, and when the building can be accessed. FRS works across Perth and regional Western Australia. Request a quote or book a free site audit.
Questions people ask
Can you give me a price over the phone?
Not a reliable one. We can usually give a sense of scale once we have seen photographs or a report.
Why survey before pricing?
The survey produces the list everyone prices against. Without it, every contractor is guessing.
Is it cheaper to fix everything at once?
Often, because access is set up once. But staging can spread the cost and keep the building running.
Do we pay more for after-hours work?
Usually, yes. Agreeing access windows early keeps it down.
Will there be variations?
Fewer if the scope is built from a survey. Hidden conditions behind linings are the usual cause.
General information, not legal advice. Your building surveyor is the right person to confirm what applies to your building.