What does a WA building surveyor need from the passive fire trade before sign-off?
Before a new Class 2 to 9 building in Western Australia can be occupied, the owner applies for an occupancy permit (form BA9). That application normally comes with a certificate of construction compliance (form BA17), signed by a registered building surveyor. To sign it, the surveyor relies on certificates and evidence from each trade. For passive fire that means a certificate of compliance for the work, the tested or assessed systems it was installed to, and a record showing where every fire-rated item is. Missing or vague passive fire evidence is one of the most common reasons sign-off gets held up.
How sign-off works in WA
- Certificate of design compliance — the building surveyor certifies the design before the building permit is issued.
- Construction — the trades build to the permitted design.
- Certificate of construction compliance (BA17) — for a new building, a registered building surveyor certifies the building was built in accordance with the permit and is suitable to occupy. The surveyor relies on technical certificates and evidence from the contractors and consultants.
- Occupancy permit (BA9) — the owner applies to the permit authority, usually the local council, with the BA17 attached.
For an existing building, a change of use, or unauthorised work, the surveyor uses a certificate of building compliance (BA18) instead.
What the surveyor will ask the passive fire trade for
- A certificate of compliance for the passive fire work, signed by the installer, stating what was installed and what it was installed to.
- The system evidence — the test reports or assessments for each system used, matching what is actually in the building.
- A register or marked-up drawings showing where every fire door, penetration, damper, fire-rated wall, bulkhead and protected steel member is.
- Labels and tags on the items themselves, matching the register.
- Photographs of work before it was closed in by ceilings and linings.
- Records for specific systems — for example dry film thickness readings for painted steel, and commissioning records for fire curtains and shutters.
- A list of any exceptions — anything that differs from the approved design, and who approved the change.
More on what a good pack contains: What should be included in a passive fire handover pack?
What holds sign-off up
- A product swapped on site without the evidence for the new product.
- Penetrations closed in by a ceiling before they were photographed or checked.
- Untagged items that cannot be matched to the register.
- A certificate with no schedule behind it, so nobody can tell what it covers.
- Late services — a trade runs new cables or pipes through a sealed wall after the passive fire work was certified.
- Fire engineering report items not closed out — for example a smoke curtain or a special door detail the report relied on.
- Fire doors with missing tags, wrong hardware, or gaps outside tolerance.
How to avoid the scramble at the end
- Agree the evidence format with the building surveyor early, not in the last week.
- Photograph and tag as you go, before linings go on.
- Lock product substitutions down: no swap without the evidence in hand.
- Control late penetrations: any trade going through a fire-rated wall after certification reports it.
- Keep one register for the job, not one per subcontractor.
After handover
The evidence does not stop being useful at the occupancy permit. Under Regulation 48A of the Building Regulations 2012, the owner must keep the building's fire integrity performing to the standard it was approved to. The handover register becomes the starting point for every inspection and maintenance visit after that. More in What does a WA building owner have to do about passive fire?
What to do next
FRS provides passive fire certification, registers and handover documentation across Perth and regional Western Australia. Send the specification and the surveyor's requirements and we will tell you what evidence is needed and when. See Documentation and handover.
Questions people ask
Who signs off passive fire in WA?
The registered building surveyor certifies the building. They rely on the installer's certificate and evidence for the passive fire work.
Is a product data sheet enough evidence?
No. The surveyor needs evidence the system was tested or assessed for how it is actually installed.
Can the building be occupied before the passive fire paperwork is finished?
A Class 2 to 9 building needs an occupancy permit before it is occupied. Temporary occupancy permits exist, but they still need a certificate from the surveyor.
Do we need photos of every penetration?
Agree it with the surveyor early. Photos taken before the ceiling went in are the best evidence you will get.
What if work has already been closed in without records?
It may need to be opened up and inspected. Talk to the surveyor and the installer before anyone starts cutting.
General information, not legal advice. Your building surveyor is the right person to confirm what applies to your building.