The building or project condition
A commercial food premises in Willetton, with electrical, mechanical, hydraulic and structural elements passing through fire-rated plasterboard walls.
What FRS delivered
- Fire stopping to electrical penetrations: power cable bundles, data cables and fire alarm cables
- Fire stopping to air conditioning pipes
- Sealing around architectural and structural elements: steel beams, purlins and top hats passing through the rated wall
- Work delivered in stages as the building progressed
What made it difficult
- Structural steel passing through the wall, which needs a different treatment from a cable or a pipe
- Four trades' services in the same walls, often close together
- Work in the roof space, at the top of the wall where most of the steel crosses it
What was recorded at close-out
- Each penetration numbered, photographed and labelled, more than fifty in all
- Certification with as-built records, as standard on FRS penetration work
The penetrations people forget are not the cables. They are the purlins and beams that run straight through the top of a fire-rated wall. Each one is a hole in the separation, and each one needs its own tested solution.
Every penetration on this job has its own number, its own folder of photographs and its own label on the wall. Anyone checking it later can match the wall to the record.