The building or project condition
A two-tower apartment development in Leederville under construction, with structural steel members at the podium and upper levels that needed a fire resistance level the bare steel could not reach.
What FRS delivered
- Design and construct of the passive fire protection to the nominated structural steel members
- Steel framing and fire-rated board systems built around the steel at Level 3 and Level 14 of both towers, including protection to the base of each member
- Systems selected against tested evidence to AS 1530.4 for each member and its required fire resistance
What made it difficult
- Two towers on one programme, with the same detail repeated at different levels
- Board protection built in place around steel already erected, with services and other trades working around it
- Work at height on an active construction site
What was recorded at close-out
- Certification with labels, as-built records and product test evidence, as standard on FRS work
Board protection is the right answer where the steel will be boxed in anyway, or where a painted coating would not suit the finish or the exposure. The framing has to follow the member, the joints have to follow the tested system, and every member has to be identifiable afterwards against the system that protects it.
This was the largest structural protection package on FRS's recent list, and it was delivered as design and construct: the system for each member was worked out by FRS, not handed down.