The building or project condition
The Level 1 data centre in a Perth CBD head office building, where new air conditioning pipework had passed through a fire-rated wall and floor.
What FRS delivered
- Fire sealing to an air conditioning pipe bundle through a two-layer plasterboard fire-rated wall
- Fire sealing to an insulated air conditioning pipe through a 200 mm concrete floor
What made it difficult
- A live data centre, where dust, debris and access are tightly controlled
- The head contractor's health, safety and environment plan and site induction before any work
- A small scope that still had to be done to the same standard as a large one
What was recorded at close-out
- Certification with penetration labels, as standard on FRS penetration work
Some jobs are two penetrations. They still need the right system, the right label and the right record, and in a data centre they need doing without leaving dust behind.
This one came through a mechanical contractor, which is how a lot of penetration work arrives: the trade that made the hole needs it sealed and certified before handover.